Dept. of Trans. PROGRESS Serial No. Contract No. 01-330-14-37 11-066004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 55% 11-SD-94-6.2/R8.8 Federal Project: ACNH-S094(47) Progress payment No. 26 Payment period ending: 11-20-01 A AND B LANDSCAPING P O BOX 720322 SAN DIEGO CA 92172 Escrow No. 01453 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,164,150.00 1,245.00 2.a. Extra Work 89,140.85 0.00 b. Adjustment Comp. -3,801.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,249,489.85 1,245.00 5. Mobilization 90,000.00 0.00 6. Total Work Completed 1,339,489.85 7. Deductions 8. a.Contract Retentions -62,474.49 -62.25 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,277,015.36 1,182.75 10. Reduction Amt to Escrow 11. Payment to Escrow 62,280.00 12. Net Pymt. this Estimate 1,182.75