Dept. of Trans. PROGRESS Serial No. Contract No. 01-267-14-12 11-066004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 51% 11-SD-94-6.2/R8.8 Federal Project: ACNH-S094(47) Progress payment No. 24 Payment period ending: 09-20-01 A AND B LANDSCAPING P O BOX 720322 SAN DIEGO CA 92172 Escrow No. 01453 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,161,700.00 1,270.00 2.a. Extra Work 89,140.85 0.00 b. Adjustment Comp. -3,801.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,247,039.85 1,270.00 5. Mobilization 90,000.00 0.00 6. Total Work Completed 1,337,039.85 7. Deductions -2,416.50 -1,000.00 8. a.Contract Retentions -62,351.99 -63.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,272,271.36 206.50 10. Reduction Amt to Escrow 11. Payment to Escrow 62,280.00 12. Net Pymt. this Estimate 206.50