Dept. of Trans. PROGRESS Serial No. Contract No. 01-141-16-01 11-066004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 42% 11-SD-94-6.2/R8.8 Federal Project: ACNH-S094(47) Progress payment No. 20 Payment period ending: 05-20-01 A AND B LANDSCAPING P O BOX 720322 SAN DIEGO CA 92172 Escrow No. 01453 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,143,685.00 1,205.00 2.a. Extra Work 89,140.85 0.00 b. Adjustment Comp. -3,801.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,229,024.85 1,205.00 5. Mobilization 90,000.00 0.00 6. Total Work Completed 1,319,024.85 7. Deductions -1,000.00 -1,000.00 8. a.Contract Retentions -61,451.24 -60.25 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,256,573.61 144.75 10. Reduction Amt to Escrow 11. Payment to Escrow 61,390.00 12. Net Pymt. this Estimate 144.75