Dept. of Trans. PROGRESS Serial No. Contract No. 01-114-15-47 11-066004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 40% 11-SD-94-6.2/R8.8 Federal Project: ACNH-S094(47) Progress payment No. 19 Payment period ending: 04-20-01 A AND B LANDSCAPING P O BOX 720322 SAN DIEGO CA 92172 Escrow No. 01453 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,142,480.00 34,350.00 2.a. Extra Work 89,140.85 0.00 b. Adjustment Comp. -3,801.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,227,819.85 34,350.00 5. Mobilization 90,000.00 0.00 6. Total Work Completed 1,317,819.85 7. Deductions 0.00 1,000.00 8. a.Contract Retentions -61,390.99 -1,717.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,256,428.86 33,632.50 10. Reduction Amt to Escrow 11. Payment to Escrow 61,390.00 12. Net Pymt. this Estimate 33,632.50