Dept. of Trans. PROGRESS Serial No. Contract No. 01-056-12-50 11-066004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 35% 11-SD-94-6.2/R8.8 Federal Project: ACNH-S094(47) Progress payment No. 17 Payment period ending: 02-20-01 A AND B LANDSCAPING P O BOX 720322 SAN DIEGO CA 92172 Escrow No. 01453 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,106,925.00 1,230.00 2.a. Extra Work 88,310.30 0.00 b. Adjustment Comp. -3,801.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,191,434.30 1,230.00 5. Mobilization 90,000.00 0.00 6. Total Work Completed 1,281,434.30 7. Deductions 8. a.Contract Retentions -59,571.72 -61.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,221,862.58 1,168.50 10. Reduction Amt to Escrow 11. Payment to Escrow 59,510.00 12. Net Pymt. this Estimate 1,168.50