Dept. of Trans. PROGRESS Serial No. Contract No. 01-024-07-20 11-066004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 33% 11-SD-94-6.2/R8.8 Federal Project: ACNH-S094(47) Progress payment No. 16 Payment period ending: 01-20-01 A AND B LANDSCAPING P O BOX 720322 SAN DIEGO CA 92172 Escrow No. 01453 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,105,695.00 1,125.00 2.a. Extra Work 88,310.30 16,349.43 b. Adjustment Comp. -3,801.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,190,204.30 17,474.43 5. Mobilization 90,000.00 0.00 6. Total Work Completed 1,280,204.30 7. Deductions 0.00 1,000.00 8. a.Contract Retentions -59,510.22 -873.73 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,220,694.08 17,600.70 10. Reduction Amt to Escrow 11. Payment to Escrow 59,510.00 12. Net Pymt. this Estimate 17,600.70