Dept. of Trans. PROGRESS Serial No. Contract No. 00-357-14-12 11-066004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 31% 11-SD-94-6.2/R8.8 Federal Project: ACNH-S094(47) Progress payment No. 15 Payment period ending: 12-20-00 A AND B LANDSCAPING P O BOX 720322 SAN DIEGO CA 92172 Escrow No. 01453 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,104,570.00 1,245.00 2.a. Extra Work 71,960.87 15,150.00 b. Adjustment Comp. -3,801.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,172,729.87 16,395.00 5. Mobilization 90,000.00 0.00 6. Total Work Completed 1,262,729.87 7. Deductions -1,000.00 0.00 8. a.Contract Retentions -58,636.49 -819.75 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,203,093.38 15,575.25 10. Reduction Amt to Escrow 11. Payment to Escrow 58,630.00 12. Net Pymt. this Estimate 15,575.25