Dept. of Trans. PROGRESS Serial No. Contract No. 00-298-14-52 11-066004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 27% 11-SD-94-6.2/R8.8 Federal Project: ACNH-S094(47) Progress payment No. 13 Payment period ending: 10-20-00 A AND B LANDSCAPING P O BOX 720322 SAN DIEGO CA 92172 Escrow No. 01453 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,102,120.00 1,270.00 2.a. Extra Work 56,810.87 0.00 b. Adjustment Comp. -3,801.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,155,129.87 1,270.00 5. Mobilization 90,000.00 0.00 6. Total Work Completed 1,245,129.87 7. Deductions -9,447.50 -1,000.00 8. a.Contract Retentions -57,756.49 -63.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,177,925.88 206.50 10. Reduction Amt to Escrow 11. Payment to Escrow 57,690.00 12. Net Pymt. this Estimate 206.50