Dept. of Trans. PROGRESS Serial No. Contract No. 10-259-10-56 09-343004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 100% 09-MNO-6-17.5/26.5 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-16-10 INTERNATIONAL SURFACING SYSTEMS P O BOX 980430 WEST SACRAMENTO CA 95798 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 771,053.44 30,101.81 2.a. Extra Work 5,426.95 0.00 b. Adjustment Comp. -11,782.65 0.00 3. Materials on Hand 4. Earned Subject to Retention 764,697.74 30,101.81 5. Mobilization 6. Total Work Completed 764,697.74 7. Deductions -90,804.23 -3,800.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 673,893.51 26,301.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,301.81