Dept. of Trans. PROGRESS Serial No. Contract No. 06-296-13-31 09-317604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 78% 09-MNO-395-93.0/120.5 Federal Project: ACNH-P395(210) Progress payment No. 07 Payment period ending: 10-20-06 B E C CONSTRUCTION CO 1645 ESMERALDA AVENUE MINDEN NV 89423 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,673,439.89 33,696.52 2.a. Extra Work 217,987.06 112,534.12 b. Adjustment Comp. -11,137.56 -11,137.56 3. Materials on Hand 4. Earned Subject to Retention 4,880,289.39 135,093.08 5. Mobilization 450,000.00 0.00 6. Total Work Completed 5,330,289.39 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,320,289.39 135,093.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 135,093.08