Dept. of Trans. PROGRESS Serial No. Contract No. 07-264-08-30 09-312104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 57% 09-INY-136-3.3/10.5 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-20-07 CIMARRON INC 10424 CIMARRON TRAIL OAKDALE CA 95361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 327,800.66 1,151.50 2.a. Extra Work 11,371.22 5,136.06 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 339,171.88 6,287.56 5. Mobilization 20,000.00 0.00 6. Total Work Completed 359,171.88 7. Deductions 8. a.Contract Retentions -16,958.59 -314.37 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 342,213.29 5,973.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,973.19