Dept. of Trans. PROGRESS Serial No. Contract No. 01-115-09-55 08-359014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 24% 30% 08-SBD-62-0.8/9.6 Federal Project: ACNH-P062(21) Progress payment No. 02 Payment period ending: 04-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01648 Total Estimate This Estimate 1. Contract Itms Without Mobil. 579,880.53 567,980.53 2.a. Extra Work 18,324.45 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 598,204.98 567,980.53 5. Mobilization 153,249.25 153,249.25 6. Total Work Completed 751,454.23 7. Deductions 8. a.Contract Retentions -59,820.50 -56,798.05 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 691,633.73 664,431.73 10. Reduction Amt to Escrow 11. Payment to Escrow 59,820.00 12. Net Pymt. this Estimate 664,431.73