Dept. of Trans. PROGRESS Serial No. Contract No. 11-112-08-50 07-3Y3804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 38% 82% 07-LA-10-C28.5/C28.5 Federal Project: NONE Progress payment No. 02 Payment period ending: 04-20-11 R P I COATING INC 10114 SHOEMAKER AVENUE SANTA FE SPRINGS CA 90670 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 123,200.00 107,000.00 2.a. Extra Work b. Adjustment Comp. 195,969.00 195,969.00 3. Materials on Hand 4. Earned Subject to Retention 319,169.00 302,969.00 5. Mobilization 25,000.00 25,000.00 6. Total Work Completed 344,169.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 344,169.00 327,969.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 327,969.00