Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-292-15-13 07-1Y5604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-1-6.8/9.2 Federal Project: NONE Progress payment No. 03 Payment period ending: 10-11-06 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 92878 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 973,889.58 217,688.00 2.a. Extra Work 11,142.81 0.00 b. Adjustment Comp. -668.24 -668.24 3. Materials on Hand 4. Earned Subject to Retention 984,364.15 217,019.76 5. Mobilization 9,000.00 0.00 6. Total Work Completed 993,364.15 7. Deductions 8. a.Contract Retentions -38,367.22 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 38,367.22 38,367.22 9. Total pay to Contractor 993,364.15 255,386.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 255,386.98