Dept. of Trans. FINAL Serial No. Contract No. 08-191-13-01 07-1X9104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-1-53.9/57.4 Federal Project: NONE Progress payment No. 07 Payment period ending: 05-01-08 D B ENGINEERING AND SITE DEVELOPMENT 2158 SCENICPARK STREET THOUSAND OAKS, CA 91362 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,000.00 0.00 2.a. Extra Work 408,674.17 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 421,674.17 0.00 5. Mobilization 6. Total Work Completed 421,674.17 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 421,674.17 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00