Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-305-08-46 07-199624 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-405-38.6/40.2 Federal Project: NONE Progress payment No. 24 Payment period ending: 09-26-07 D W POWELL CONSTRUCTION INC 8555 BANANA AVE FONTANA CA 92335-3019 Escrow No. 02212 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,126,045.96 -62,775.00 2.a. Extra Work 90,944.24 18,424.89 b. Adjustment Comp. 290,037.06 44,958.60 3. Materials on Hand 4. Earned Subject to Retention 3,507,027.26 608.49 5. Mobilization 330,000.00 0.00 6. Total Work Completed 3,837,027.26 7. Deductions 8. a.Contract Retentions -175,320.94 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 175,320.94 175,320.94 9. Total pay to Contractor 3,837,027.26 175,929.43 10. Reduction Amt to Escrow -175,170.00 -175,170.00 11. Payment to Escrow 175,170.00 12. Net Pymt. this Estimate 759.43