Dept. of Trans. PROGRESS Serial No. Contract No. 04-146-14-11 07-181604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 64% 07-LA-91-R14.0/R20.7 Federal Project: ACNH-P091(112) Progress payment No. 21 Payment period ending: 05-20-04 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE STREET BALDWIN PARK CA 917061747 Escrow No. 01994 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,454,706.12 648,576.31 2.a. Extra Work 600,153.37 40,363.98 b. Adjustment Comp. 2,876.35 4,376.35 3. Materials on Hand 131,066.56 -20,974.74 4. Earned Subject to Retention 10,188,802.40 672,341.90 5. Mobilization 1,780,000.00 0.00 6. Total Work Completed 11,837,735.84 7. Deductions 8. a.Contract Retentions -509,440.12 -33,617.09 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,459,362.28 638,724.81 10. Reduction Amt to Escrow 11. Payment to Escrow 509,440.00 12. Net Pymt. this Estimate 638,724.81