Dept. of Trans. PROGRESS Serial No. Contract No. 11-299-10-35 07-166814 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-10-18.3/31.3 Federal Project: ER-ACIM(10) Progress payment No. 38 Payment period ending: 10-20-11 ATKINSON CONTRACTORS L P 27422 PORTOLA PARKWAY STE 250 FOOTHILL RANCH CA 92610 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 100,884,251.16 3,590,064.07 2.a. Extra Work 2,307,258.48 101,739.96 b. Adjustment Comp. 2,411,754.64 0.00 3. Materials on Hand 258,859.20 -129,541.25 4. Earned Subject to Retention 105,862,123.48 3,562,262.78 5. Mobilization 11,820,000.00 0.00 6. Total Work Completed 117,423,264.28 7. Deductions -164,500.00 -50,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 117,517,623.48 3,512,262.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,512,262.78