Dept. of Trans. PROGRESS Serial No. Contract No. 03-203-10-48 07-1069U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 59% 50% 07-LA-10-28.0/31.2 Federal Project: ACNH-010-1(762) I-010-1(762) Progress payment No. 23 Payment period ending: 07-20-03 E L YEAGER CONSTRUCTION COMPANY INC P O BOX 87 RIVERSIDE CA 925020087 Escrow No. 01885 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,773,848.56 843,458.35 2.a. Extra Work 564,848.25 31,267.67 b. Adjustment Comp. -8,106.18 0.00 3. Materials on Hand 411,831.58 0.00 4. Earned Subject to Retention 21,742,422.21 874,726.02 5. Mobilization 3,712,000.00 0.00 6. Total Work Completed 25,042,590.63 7. Deductions -46,240.00 0.00 8. a.Contract Retentions -1,087,121.11 -43,736.30 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 24,321,061.10 830,989.72 10. Reduction Amt to Escrow 11. Payment to Escrow 1,000,000.00 12. Net Pymt. this Estimate 830,989.72