Dept. of Trans. PROGRESS Serial No. Contract No. 09-266-14-49 07-0510C4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-5-28.1/28.6 Federal Project: NONE Progress payment No. 38 Payment period ending: 09-20-09 P AND D LANDSCAPE MANAGEMENT SERVICES 999 TOWN AND COUNTRY RD 4 FLR ORANGE CA 92868 Escrow No. 02242 Total Estimate This Estimate 1. Contract Itms Without Mobil. 329,562.02 1,944.28 2.a. Extra Work 9,964.50 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 339,526.52 1,944.28 5. Mobilization 20,000.00 0.00 6. Total Work Completed 359,526.52 7. Deductions 8. a.Contract Retentions -16,976.33 -97.22 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 342,550.19 1,847.06 10. Reduction Amt to Escrow 11. Payment to Escrow 16,870.00 12. Net Pymt. this Estimate 1,847.06