Dept. of Trans. PROGRESS Serial No. Contract No. 07-115-13-28 06-407204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 63% 06-MAD-99-9.1/9.8 Federal Project: 06-MAD-145-8.9/9.2 NH Progress payment No. 06 Payment period ending: 04-20-07 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,328,940.87 855,961.32 2.a. Extra Work 84,578.83 11,774.34 b. Adjustment Comp. -2,681.95 -2,062.38 3. Materials on Hand 15,617.60 -101,285.00 4. Earned Subject to Retention 3,426,455.35 764,388.28 5. Mobilization 90,000.00 4,500.00 6. Total Work Completed 3,500,837.75 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -171,322.77 -38,219.42 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,335,132.58 730,668.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 730,668.86