Dept. of Trans. PROGRESS Serial No. Contract No. 07-081-13-31 06-407204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 44% 51% 06-MAD-99-9.1/9.8 Federal Project: 06-MAD-145-8.9/9.2 NH Progress payment No. 05 Payment period ending: 03-20-07 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,472,979.55 400,933.86 2.a. Extra Work 72,804.49 5,109.97 b. Adjustment Comp. -619.57 0.00 3. Materials on Hand 116,902.60 116,902.60 4. Earned Subject to Retention 2,662,067.07 522,946.43 5. Mobilization 85,500.00 0.00 6. Total Work Completed 2,630,664.47 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -133,103.35 -16,397.64 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,604,463.72 496,548.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 496,548.79