Dept. of Trans. PROGRESS Serial No. Contract No. 04-055-06-21 06-342424 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 54% 06-FRE-180-R60.3/R64.0 Federal Project: ACNH-P180(44) Progress payment No. 19 Payment period ending: 02-20-04 E L YEAGER CONSTRUCTION COMPANY INC P O BOX 87 RIVERSIDE CA 925020087 Escrow No. 02019 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,001,727.10 777,872.75 2.a. Extra Work 745,918.21 73,067.87 b. Adjustment Comp. 273,492.14 -14,427.49 3. Materials on Hand 1,219,021.32 29,328.87 4. Earned Subject to Retention 26,240,158.77 865,842.00 5. Mobilization 4,900,000.00 0.00 6. Total Work Completed 29,921,137.45 7. Deductions -83,600.00 -60,000.00 8. a.Contract Retentions -1,312,007.94 -43,292.10 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 29,744,550.83 762,549.90 10. Reduction Amt to Escrow 11. Payment to Escrow 1,312,000.00 12. Net Pymt. this Estimate 762,549.90