Dept. of Trans. PROGRESS Serial No. Contract No. 08-297-05-35 06-0E6904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 21% 28% 06-KER-395-0.1/T14.6 Federal Project: ACHS-P395(219) NH-P395(219) Progress payment No. 02 Payment period ending: 10-20-08 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,112,573.17 1,080,634.77 2.a. Extra Work 5,134.51 5,134.51 b. Adjustment Comp. -40,306.94 -40,306.94 3. Materials on Hand 4. Earned Subject to Retention 1,077,400.74 1,045,462.34 5. Mobilization 324,141.00 324,141.00 6. Total Work Completed 1,401,541.74 7. Deductions -376.80 -376.80 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,401,164.94 1,369,226.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,369,226.54