Dept. of Trans. PROGRESS Serial No. Contract No. 09-327-08-25 05-330714 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 05-SLO-46-32.2/37.2 Federal Project: HPLU-6205(10) HP21-6205(12) L-6205(12) Progress payment No. 22 Payment period ending: 11-20-09 PAPICH CONSTRUCTION COMPANY INC P O BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,655,405.76 2,331,068.20 2.a. Extra Work 430,386.66 821.28 b. Adjustment Comp. 144,577.86 -43,439.52 3. Materials on Hand 644,884.00 -67,023.00 4. Earned Subject to Retention 15,875,254.28 2,221,426.96 5. Mobilization 20,000.00 1,000.00 6. Total Work Completed 15,250,370.28 7. Deductions -143,575.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,751,679.28 2,222,426.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,222,426.96