Dept. of Trans. PROGRESS Serial No. Contract No. 11-264-10-35 05-315924 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 38% 53% 05-MON-1-99.9/R101.5 Federal Project: NONE Progress payment No. 21 Payment period ending: 09-20-11 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,564,724.01 337,924.15 2.a. Extra Work 196,508.71 9,137.32 b. Adjustment Comp. -6,850.20 0.00 3. Materials on Hand 144,023.96 0.00 4. Earned Subject to Retention 3,898,406.48 347,061.47 5. Mobilization 950,000.00 0.00 6. Total Work Completed 4,704,382.52 7. Deductions -10,447.24 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,837,959.24 347,061.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 347,061.47