Dept. of Trans. FINAL Serial No. Contract No. 08-249-09-08 04-272014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SCL-280-R2.2/5.1 Federal Project: NONE Progress payment No. 26 Payment period ending: 07-02-08 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 02245 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,680,141.45 0.00 2.a. Extra Work 965,596.02 0.00 b. Adjustment Comp. 25,199.70 0.00 3. Materials on Hand 4. Earned Subject to Retention 14,670,937.17 0.00 5. Mobilization 1,747,000.00 0.00 6. Total Work Completed 16,417,937.17 7. Deductions -149,226.00 0.00 8. a.Contract Retentions -733,371.86 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 733,371.86 0.00 9. Total pay to Contractor 16,268,711.17 0.00 10. Reduction Amt to Escrow -733,240.00 0.00 11. Payment to Escrow 733,240.00 12. Net Pymt. this Estimate 0.00