Dept. of Trans. PROGRESS Serial No. Contract No. 07-166-08-45 04-272014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 83% 04-SCL-280-R2.2/5.1 Federal Project: NONE Progress payment No. 12 Payment period ending: 06-20-07 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 02245 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,563,843.71 1,205,626.11 2.a. Extra Work 588,109.25 239,389.60 b. Adjustment Comp. 3,568.60 0.00 3. Materials on Hand 4. Earned Subject to Retention 12,155,521.56 1,445,015.71 5. Mobilization 1,747,000.00 0.00 6. Total Work Completed 13,902,521.56 7. Deductions -222,772.50 7,752.00 8. a.Contract Retentions -607,776.08 -72,250.79 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,071,972.98 1,380,516.92 10. Reduction Amt to Escrow 11. Payment to Escrow 607,770.00 12. Net Pymt. this Estimate 1,380,516.92