Dept. of Trans. PROGRESS Serial No. Contract No. 07-139-07-53 04-272014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 75% 74% 04-SCL-280-R2.2/5.1 Federal Project: NONE Progress payment No. 11 Payment period ending: 05-20-07 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 02245 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,358,217.60 526,400.71 2.a. Extra Work 348,719.65 288,000.00 b. Adjustment Comp. 3,568.60 3,568.60 3. Materials on Hand 4. Earned Subject to Retention 10,710,505.85 817,969.31 5. Mobilization 1,747,000.00 0.00 6. Total Work Completed 12,457,505.85 7. Deductions -230,524.50 0.00 8. a.Contract Retentions -535,525.29 -40,898.46 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,691,456.06 777,070.85 10. Reduction Amt to Escrow 11. Payment to Escrow 535,520.00 12. Net Pymt. this Estimate 777,070.85