Dept. of Trans. PROGRESS Serial No. Contract No. 12-297-12-40 04-264144 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 33% 62% 04-NAP-12-2.8/3.3 Federal Project: 04-SOL-12-0.0/R2.6 ACST-P102(107) P-P102(107) Progress payment No. 11 Payment period ending: 10-20-12 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,427,654.85 1,995,610.35 2.a. Extra Work 524,170.07 363,098.17 b. Adjustment Comp. 150,762.00 0.00 3. Materials on Hand 844,270.15 267,120.97 4. Earned Subject to Retention 9,946,857.07 2,625,829.49 5. Mobilization 3,087,500.00 0.00 6. Total Work Completed 12,190,086.92 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,034,357.07 2,625,829.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,625,829.49