Dept. of Trans. PROGRESS Serial No. Contract No. 09-264-14-56 04-253784 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 48% 45% 04-ALA-680-0.0/R303.0 Federal Project: 04-SCL-680-7.4/9.9 NONE Progress payment No. 05 Payment period ending: 09-20-09 TOP GRADE CONSTRUCTION INC 50 CONTRACTORS STREET LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,929,851.67 2,321,499.50 2.a. Extra Work 176,380.52 42,264.10 b. Adjustment Comp. 3. Materials on Hand 137,678.18 82,437.53 4. Earned Subject to Retention 11,243,910.37 2,446,201.13 5. Mobilization 1,722,350.00 0.00 6. Total Work Completed 12,828,582.19 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,966,260.37 2,446,201.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,446,201.13