Dept. of Trans. PROGRESS Serial No. Contract No. 06-263-07-49 04-252064 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 98% 04-CC-4-12.4/ .0 Federal Project: NONE Progress payment No. 08 Payment period ending: 09-20-06 SPOSETO ENGINEERING INC 4301 BETTENCOURT WAY UNION CITY CA 94587 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 486,348.56 24,629.31 2.a. Extra Work 19,966.96 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 506,315.52 24,629.31 5. Mobilization 10,000.00 0.00 6. Total Work Completed 516,315.52 7. Deductions -3,545.00 0.00 8. a.Contract Retentions -25,315.78 -1,231.47 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 487,454.74 23,397.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,397.84