Dept. of Trans. PROGRESS Serial No. Contract No. 05-110-09-27 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 83% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 33 Payment period ending: 04-20-05 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,168,371.88 483,176.54 2.a. Extra Work 16,227,430.42 240,242.90 b. Adjustment Comp. -2,746,951.58 365,167.68 3. Materials on Hand 1,562,842.97 -627,312.86 4. Earned Subject to Retention 41,211,693.69 461,274.26 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 43,498,850.72 7. Deductions 8. a.Contract Retentions -2,060,584.68 -23,063.71 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 43,001,109.01 438,210.55 10. Reduction Amt to Escrow 11. Payment to Escrow 2,060,580.00 12. Net Pymt. this Estimate 438,210.55