Dept. of Trans. SEMI-FINAL Serial No. Contract No. 12-300-10-57 03-3M7104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SAC-160-5.9/21.1 Federal Project: NONE Progress payment No. 14 Payment period ending: 09-05-12 SANTA MARGARITA CONSTRUCTION CORP P O BOX 357 TEMPLETON CA 93465 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,083,512.64 0.00 2.a. Extra Work 83,848.15 43,788.87 b. Adjustment Comp. -67,561.14 -2,500.00 3. Materials on Hand 4. Earned Subject to Retention 6,099,799.65 41,288.87 5. Mobilization 697,760.00 0.00 6. Total Work Completed 6,797,559.65 7. Deductions -56,473.23 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,741,086.42 41,288.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 41,288.87