Dept. of Trans. PROGRESS Serial No. Contract No. 10-172-13-42 03-1E0304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 33% 24% 03-COL-20-R21.5/R22.4 Federal Project: SARR-P020(150) A-P020(150) Progress payment No. 05 Payment period ending: 06-18-10 NORTH BAY CONSTRUCTION INC P O BOX 6004 PETALUMA CA 949556004 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,664,550.55 1,496,941.05 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 179,572.95 -746,243.67 4. Earned Subject to Retention 1,844,123.50 750,697.38 5. Mobilization 147,250.00 0.00 6. Total Work Completed 1,811,800.55 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,991,373.50 750,697.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 750,697.38