Dept. of Trans. SEMI-FINAL Serial No. Contract No. 06-201-07-47 03-1A8904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-YOL-80-0.0/0.4 Federal Project: ACIM-X113(27) Progress payment No. 23 Payment period ending: 11-18-05 BAUMAN LANDSCAPE INC 115 BROOKSIDE DRIVE RICHMOND CA 94801 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,251,083.41 -21,759.39 2.a. Extra Work 113,275.24 31,641.89 b. Adjustment Comp. 620,221.02 3,308.01 3. Materials on Hand 4. Earned Subject to Retention 2,984,579.67 13,190.51 5. Mobilization 6. Total Work Completed 2,984,579.67 7. Deductions -115,953.33 0.00 8. a.Contract Retentions -138,374.94 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 138,374.94 0.00 9. Total pay to Contractor 2,868,626.34 13,190.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,190.51