Dept. of Trans. PROGRESS Serial No. Contract No. 12-326-14-05 03-1A73U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 42% 03-ED-50-77.3/79.3 Federal Project: NH Progress payment No. 21 Payment period ending: 11-20-12 DISNEY CONSTRUCTION INC 875 MAHLER ROAD STE 188 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,630,107.70 91,986.12 2.a. Extra Work 1,244,331.59 71,774.70 b. Adjustment Comp. 657,248.71 0.00 3. Materials on Hand 4. Earned Subject to Retention 12,531,688.00 163,760.82 5. Mobilization 1,080,000.00 0.00 6. Total Work Completed 13,611,688.00 7. Deductions -77,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,534,688.00 153,760.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 153,760.82