Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 12-353-16-41 02-3E6104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-PLU-70-9.0/ .0 Federal Project: NONE Progress payment No. 06 Payment period ending: 11-16-12 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,782,755.20 9,621.80 2.a. Extra Work 56,877.19 14,885.94 b. Adjustment Comp. -7,388.23 -7,388.23 3. Materials on Hand 4. Earned Subject to Retention 1,832,244.16 17,119.51 5. Mobilization 190,000.00 0.00 6. Total Work Completed 2,022,244.16 7. Deductions -102,465.00 -89,076.77 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,919,779.16 -71,957.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -71,957.26