Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-353-16-22 02-381114 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-SIS-5-R11.4/R16.0 Federal Project: ACIM-005-9(164) Progress payment No. 09 Payment period ending: 11-15-06 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049-4519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,121,330.56 553,184.02 2.a. Extra Work 165,229.01 12,725.17 b. Adjustment Comp. -57,555.76 -46,709.59 3. Materials on Hand 4. Earned Subject to Retention 12,229,003.81 519,199.60 5. Mobilization 900,000.00 0.00 6. Total Work Completed 13,129,003.81 7. Deductions -45,685.26 53,614.74 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,083,318.55 572,814.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 572,814.34