Dept. of Trans. PROGRESS Serial No. Contract No. 06-206-09-58 02-381114 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 40% 41% 02-SIS-5-R11.4/R16.0 Federal Project: ACIM-005-9(164) Progress payment No. 05 Payment period ending: 07-20-06 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049-4519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,515,767.59 1,881,531.91 2.a. Extra Work 82,566.90 33,935.70 b. Adjustment Comp. -15,099.09 4,521.61 3. Materials on Hand 92,690.83 0.00 4. Earned Subject to Retention 4,675,926.23 1,919,989.22 5. Mobilization 855,000.00 0.00 6. Total Work Completed 5,438,235.40 7. Deductions -79,300.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,451,626.23 1,919,989.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,919,989.22