Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 10-362-09-13 01-3116U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-MEN-253-0.5/3.5 Federal Project: ACST-X045(20) P-X045(20) ACBH-X045(20) Progress payment No. 29 Payment period ending: 09-22-10 VIKING CONSTRUCTION COMPANY INC P O BOX 1508 RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,378,409.97 7,952.50 2.a. Extra Work 583,334.46 140,982.51 b. Adjustment Comp. -8,632.93 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,953,111.50 148,935.01 5. Mobilization 375,000.00 0.00 6. Total Work Completed 4,328,111.50 7. Deductions -113,685.04 -20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,214,426.46 128,935.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 128,935.01