Dept. of Trans. PROGRESS Serial No. Contract No. 02-203-09-45 01-275704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 44% 56% 01-HUM-5727 Federal Project: NONE Progress payment No. 06 Payment period ending: 07-19-02 SEQUOIA CONSTRUCTION SPECIALTIES P O BOX 6061 EUREKA CA 95502 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 343,545.00 72,732.50 2.a. Extra Work 3,727.00 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 347,272.00 72,732.50 5. Mobilization 6. Total Work Completed 347,272.00 7. Deductions 8. a.Contract Retentions -17,363.60 -1,586.84 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 329,908.40 71,145.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 71,145.66