Dept. of Trans. PROGRESS Serial No. Contract No. 02-116-10-41 01-230014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 53% 01-LAK-29-9.4/9.9 Federal Project: ACST-P029(85) P-P029(85) Progress payment No. 17 Payment period ending: 04-19-02 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 960491539 Escrow No. 01700 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,743,929.15 191,050.00 2.a. Extra Work 89,324.04 0.00 b. Adjustment Comp. 22,118.02 0.00 3. Materials on Hand 109,619.63 -26,979.55 4. Earned Subject to Retention 2,964,990.84 164,070.45 5. Mobilization 500,000.00 0.00 6. Total Work Completed 3,355,371.21 7. Deductions -2,163.50 0.00 8. a.Contract Retentions -148,249.54 -8,203.52 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,314,577.80 155,866.93 10. Reduction Amt to Escrow 11. Payment to Escrow 148,240.00 12. Net Pymt. this Estimate 155,866.93