Dept. of Trans. PROGRESS Serial No. Contract No. 01-330-11-29 01-230014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 56% 37% 01-LAK-29-9.4/9.9 Federal Project: ACST-P029(85) P-P029(85) Progress payment No. 11 Payment period ending: 11-20-01 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 960491539 Escrow No. 01700 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,339,592.82 254,198.32 2.a. Extra Work 76,293.98 -6.76 b. Adjustment Comp. 19,895.57 0.00 3. Materials on Hand 92,072.42 -122,728.80 4. Earned Subject to Retention 2,527,854.79 131,462.76 5. Mobilization 500,000.00 25,000.00 6. Total Work Completed 2,935,782.37 7. Deductions 8. a.Contract Retentions -126,392.74 -6,573.14 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,901,462.05 149,889.62 10. Reduction Amt to Escrow 11. Payment to Escrow 126,390.00 12. Net Pymt. this Estimate 149,889.62