Dept. of Trans. PROGRESS Serial No. Contract No. 01-205-10-36 01-230014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 36% 18% 01-LAK-29-9.4/9.9 Federal Project: ACST-P029(85) P-P029(85) Progress payment No. 07 Payment period ending: 07-20-01 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 960491539 Escrow No. 01700 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,309,973.62 293,903.94 2.a. Extra Work 70,590.22 -1,234.44 b. Adjustment Comp. 7,612.50 0.00 3. Materials on Hand 32,051.42 -184,343.16 4. Earned Subject to Retention 1,420,227.76 108,326.34 5. Mobilization 475,000.00 0.00 6. Total Work Completed 1,863,176.34 7. Deductions 8. a.Contract Retentions -93,505.95 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,801,721.81 108,326.34 10. Reduction Amt to Escrow 11. Payment to Escrow 93,500.00 12. Net Pymt. this Estimate 108,326.34