Dept. of Trans. PROGRESS Serial No. Contract No. 01-173-10-42 01-230014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 30% 13% 01-LAK-29-9.4/9.9 Federal Project: ACST-P029(85) P-P029(85) Progress payment No. 06 Payment period ending: 06-20-01 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 960491539 Escrow No. 01700 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,016,069.68 454,334.33 2.a. Extra Work 71,824.66 45,427.71 b. Adjustment Comp. 7,612.50 7,612.50 3. Materials on Hand 216,394.58 -7,792.88 4. Earned Subject to Retention 1,311,901.42 499,581.66 5. Mobilization 475,000.00 100,000.00 6. Total Work Completed 1,570,506.84 7. Deductions 8. a.Contract Retentions -93,505.95 -12,273.97 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,693,395.47 587,307.69 10. Reduction Amt to Escrow 11. Payment to Escrow 93,500.00 12. Net Pymt. this Estimate 587,307.69