Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 01-156-13-10 01-230014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 19% 8% 01-LAK-29-9.4/9.9 Federal Project: ACST-P029(85) P-P029(85) Progress payment No. 05 Payment period ending: 05-18-01 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 960491539 Escrow No. 01700 Total Estimate This Estimate 1. Contract Itms Without Mobil. 561,735.35 0.00 2.a. Extra Work 26,396.95 2,476.83 b. Adjustment Comp. 3. Materials on Hand 224,187.46 0.00 4. Earned Subject to Retention 812,319.76 2,476.83 5. Mobilization 375,000.00 0.00 6. Total Work Completed 963,132.30 7. Deductions 0.00 121,442.93 8. a.Contract Retentions -81,231.98 -247.69 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,106,087.78 123,672.07 10. Reduction Amt to Escrow 11. Payment to Escrow 80,980.00 12. Net Pymt. this Estimate 123,672.07