Pine Rehab(ilitation) Project
Inyo County - Highway 395 - Post Mile 99.0 to
100.8
Project
Location:
The
project is located on U.S. Highway 395 in Inyo
County in and near the community of Big Pine.
The project limits extend from Big Pine
Dump Road to the south junction of State Route
168.
Click
on the highlighted links below to view. After
viewing, click the "Back" button on your browser
to return to this page.
Project
Description:
This
project is a State Highway Operation and Protection
Program (SHOPP) roadway rehabilitation project
with the focus on preservation and extension
of the service life of the roadway. Other enhancements
include:
1. Construction of a twelve-foot
two-way left-turn lane in the center of the
roadway (from Big Pine Dump Road to the intersection
with State Route 168),
2.
Eight-foot shoulders (allowing for parking)
on both sides,
3.
Continuous sidewalks constructed on both sides
of the highway from Bartell Road to Baker
Road.
Project
Status:
The
project is in the Final Design (How
A Project Gets Built) phase, and design
of the approved alternative is in progress.
| Estimated
total project cost (support and capital) |
$6,411,000.00 |
| Date
Project Scoping and Summary Report (PSSR) approved |
August
31, 1999 |
| Date
Environmental Document approved |
January
31, 2002 |
| Date
project approved (PA&ED) |
January
31, 2002 |
| Date
final design completed and project Ready
to List (RTL) |
November 11,
2004 |
| Date
project advertised (HQ Advertise) |
March
1, 2004 |
| Date
of bid opening |
March
30, 2004 |
| Date
contract with contractor (Sierra Nevada
Construction, Inc.) approved |
April
19, 2004 |
| Beginning
of construction (first contract working
day) |
May
4, 2004 |
| Beginning of Stage 1 (construction on west) |
May
10, 2004 |
| Beginning of Stage 2 (construction on east) |
July 8, 2004 |
| Estimated
completion of construction (Contract Acceptance)
|
September
2004 |
For
more details please see Project Status.
Project Funding:
This
project was funded through Roadway Preservation
(Roadway Rehabilitation) and programmed in the
2000 State Highway Operation and Protection
Program (SHOPP).
Project
Information:
| Prime
Contractor: Sierra Nevada Construction, Inc (from Sparks,
Nevada). |
| Construction:
Construction of the project
will occur in three stages Construction
Staging (note: plans may vary at time
of construction). The roadway and
sidewalks will be constructed half-width
at a time in stages 1 and 2. Stage
1 involves construction along
the west half of the highway and one lane
of traffic in each direction on the east
half of the roadway. Stage 2
redirects one lane of traffic in each
direction to the west half of the roadway
and construction occurs along the east
half of the highway. Stage 3
consists of an asphalt concrete overlay
across the entire roadway and placing
final stripe. Each stage is expected to
take about 8 weeks to construct. During
this period, at least one access point
will be provided to adjacent residences,
businesses, and facilities at all times.
There will be no parking on either side
of town during the duration of construction
activities. |
| Project
map: Big Pine Rehab |
| Photos:
(taken after completion of Stage 1-looking
south) n/o Blake St.,
s/o Chestnut St.,
s/o Baker Creek Rd. |
Project
Manager:
This
page last updated in July 2004 |