Manzanar Four-Lane Project
Manzanar Four-Lane Project
Inyo County - Highway 395 - Post Mile 65.0 to 71.2
Project Location:
This project is located on U.S. Highway 395 in Inyo County. The project limits extend from 7.6 miles north of Lone Pine to 2.0 miles south of Independence.
Click on the highlighted links below to view. After viewing, click the "Back" button on your browser to return to this page.
|
|
Project Description:
Project Status:
The project is in the Final Design (How A Project Gets Built) phase, and design of the selected alternative is in progress. The schedule shown below is dependent on the future availability of funds.
| Estimated total project cost (support and capital) |
$20,697,000.00
|
| Beginning of Environmental and Design Studies |
July 1, 1998
|
| Completion of Environmental and Design Studies (PA&ED) |
May 14, 2004
|
| Date project alternative approved (PA&ED) |
May 14, 2004
|
| Estimated beginning of construction date (Approve Contract) |
w
inter 2007/08
|
| Estimated completion of construction date (Contract Acceptance) |
winter 2009/10
|
For more details please see Project Status.
Project Funding:
This project was funded through the Interregional Transportation Improvement Program (ITIP) and programmed in the 1998 State Transportation Improvement Program (STIP).
Project Information:
| Final Environmental Document: Negative Declaration/Finding Of No Significant Impact (ND/FONSI) |
| Project Map: Manzanar Four-Lane |
| Proposed Project Phasing (if necessary): Project Phasing |
Project Manager:
| Bryan Winzenread |
| 500 S. Main Street |
| Bishop, CA 93514 |
| 760-872-5250 |
| Email: Bryan_Winzenread@dot.ca.gov |
This page was last updated in July 2004