The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.


Q1) Bid item 7 shows to bid based on a SF Unit of Measure, but the Roadway Quantities on the plans show the unit of measure as SY's, looks like the bid sheets are wrong since this type of work is normally bid by the SY, if it is bid by the SF this item will overrun by a bunch.

A1) Submitted for consideration. 2May11.